Concrete Pours — The Bucket and the Pump (Part 1 of 2)

Lines in italics are for the reader, not the crew. How to read a talk

Printable version with sign-in sheet (PDF)

Read this out loud

Morning, everybody. Pour day. Everybody's moving fast, the truck is waiting, the concrete is setting whether we're ready or not. This is part one of two. Part two is tools on the deck, forms and shoring.

The bucket

Nobody works under a concrete bucket while it's going up or coming down into place, whatever is lifting it. Vibrator crews too: stay out from under a bucket hanging from a crane or cableway. Where it can be done, the bucket's route is planned so nobody, or as few people as possible, is under its path.

Nobody rides a concrete bucket. For any reason.

Buckets with hydraulic or air gates have a safety latch so they can't dump early. If the latch is missing or broken, say so before the bucket flies.

The pump and the hose

The end hose that swings free, the whip hose, gets nothing hung on it. No hooks, no valves, no add-ons. And a hose with couplings on both ends is not used as a whip hose. If it lets go, a coupling on the end becomes a hammer.

The placing boom places concrete. It is not used to drag hoses around or to lift anything else. The pump sits on its outriggers set the way the maker says.

Nobody stands on the guard over the pump's agitator while the pump or agitator is running. The pump must have a clearly labeled emergency stop. Knowing where it is before the pour starts is on you; that part is good practice.

The pipe that carries the concrete is supported and anchored so it can't move or overload the clamps. Pipe clamps are rated at least to the pump's pressure and kept clean where they grip. If quick-connect clamps are used on a vertical run, they are pinned or secured so they can't open. And the rule says no pumping through grooved-end couplers.

Cleaning out the line

When they blow out the pump line with compressed air, the pipe is anchored first. The flexible discharge hose comes off. A trap basket or containment device is there, secured, to catch the clean-out device. The air system has a shutoff valve, and the blow-out caps have a bleeder valve to relieve the pressure. Anybody not needed for the cleaning leaves the area. And delivery pipes are depressurized before clamps and fittings come loose.

If an inspection finds something that could hurt someone, the pump or boom doesn't go back to work until it's fixed. After a structural failure, an overload or touching a power line, it is certified safe by the maker, the maker's agent or a professional engineer first.

The truck

Ready-mix truck on a slope while it's discharging? Wheels blocked, brakes set.

Talk it over

  1. Where will the bucket or boom be swinging today, and who might be under it?
  2. Where is the pump's emergency stop, and who is staying out of the clean-out area?

Before you go

Never under the bucket. Nothing on the whip hose. Everybody clear for the blow-out.

Short on time, or no one to lead it? Doc and Red can run this talk for you in the R Safety Hub app.

Get started

Reference (not read aloud). Washington: WAC 296-155-682(9)(a), (c), (d) (bucket safety latches; riding buckets prohibited; vibrator crews kept out from under buckets suspended from cranes or cableways; ready-mix trucks blocked and braked when discharging on a slope), (8)(b)(iii) (equipment that could endanger workers not returned to service until corrected), (8)(b)(ix) (clearly labeled emergency stop), (8)(b)(x)(C) (no one stands on the agitator guard while running), (8)(b)(xi)(A) (outriggers per the maker's specifications), (8)(b)(xii)(B) (placing boom not used to drag hoses or lift other loads), (8)(b)(xiv)(A), (C), (D) (no pumping through grooved-end couplers; clamp contact surfaces free of concrete; quick-connect clamps pinned or secured in vertical use), (8)(b)(xv)(A), (B), (C) (delivery pipe supported and anchored; double ended hoses not used as whip hoses; no attachments on whip hoses), (8)(b)(xix)(A), (B), (C), (F), (G) (compressed air cleaning: pipe anchored, flexible discharge hose removed, workers not essential leave, trap basket or containment device, pipes depressurized before clamps are released); 296-155-680(13)(a), (b) (no employee under concrete buckets while being elevated or lowered into position; routes planned so no one, or the fewest, are exposed). Federal: 29 CFR 1926.701, .702, .703. Differences seen: the whip hose, placing boom, agitator guard, emergency stop, clamp, clean-out and ready-mix truck lines were read in the Washington text only. "Know where the emergency stop is" (labelled aloud) is good practice, not rule text.