Morning, everybody. This is part two about pour day. Part one was the bucket, the pump and the hose. Today is the tools on the deck, the forms and the shoring.
Tools on the deck
Bull float handles that could touch an energized conductor are made of material that doesn't conduct electricity, or covered with a sleeve that does the same job. Look up before you swing a long handle.
A walk-behind power trowel has a switch that shuts it off when your hands come off the handles. If somebody has rigged it to keep running, don't use it, and tell your supervisor. That part is good sense.
Concrete buggy handles don't stick out past the wheels on either side. If you're spraying a cement, sand and water mix through an air hose, you wear head and face protection.
And where an accidental start-up could injure someone, nobody does maintenance or repair on a mixer, pump or compressor until its energy is locked out and tagged.
Forms and shoring
During the pour, the form supports and wedges get checked so they don't shift or fail. The shoring is inspected right before, during and right after the pour. A shoring layout from a qualified person is on the job site, and the setup follows it. If conditions in the field call for a change, the person who made the layout has to approve it before the concrete goes in. Shoring that is damaged or weakened is removed and replaced immediately.
Vertical shoring is plumb, no more than an eighth of an inch off in three feet. If it's off more than that, it isn't used until it's readjusted. If anything starts to bulge, crack, creak or move, call it out and get people clear. The concrete can wait. You can't be replaced.
Forms don't come off until the concrete is cured and set enough to be stripped safely. How long they stay follows the engineer's specs and local building codes, and tests on field-cured samples have to show the concrete is strong enough. Shoring doesn't come out without a qualified engineer's approval, and it is taken out to a plan so what's left isn't overloaded. Our plain sense: stripping early is how a slab comes down.
When a crane, cableway or hoist moves forms, they are attached to slings with a safety factor of at least five. No. 9 tie wire, fiber rope and similar makeshift lashing are not allowed. Large panels get taglines. When forms are being raised or taken off in sections, vertical or overhead, nobody lets go of a section until it is braced or secured. People at lower levels are protected from falling material, and walkways get warning signs.
And every bar sticking up that someone could fall onto or into must be guarded. A cover is one example. Working on the face of the forms or the rebar at four feet or more, you use personal fall arrest, a positioning device or a safety net.
Talk it over
- Who is watching the forms and shores while we pour, and how do they stop the pour?
- Which bars are sticking up, and what is covering them?
Before you go
Watch the forms. Plumb shoring, layout on site. Nothing comes out early. Lock it out before you reach in.