Morning, everybody. Today is about demolition. Tearing a building down, or tearing part of one out.
Demolition looks like the easy end of construction. No level, no tape measure, just a pry bar and an opinion. But a building that is coming apart gets weaker as we go, and it does not tell us which part is next.
This is the short version. Washington's demolition rule has more in it than one talk can hold, like chutes, floor removal and machines. These are the parts most crews run into.
Before anybody swings
Before anybody swings, there is a lot to do, and most of it is the company's job. A competent person, someone the company picks for this work, checks the building over before it starts, and there is a written plan for this job. The competent person for demolition is not always the same person who checks the scaffold. Utilities get shut off or controlled. The building gets checked for asbestos and other hazardous materials, and anything found comes out first. Glass that could fly gets taken out. And a building already damaged by fire, flood or an explosion gets shored or braced before anyone goes inside.
You do not need to know every step. You need to know who the competent person is. If something looks skipped, ask your supervisor before you start.
Top down
Apart from prep work, like cutting holes for chutes, outside walls and floors come down from the top. One story at a time. Each story is removed and dropped into the storage space before the next one down is started.
Nobody does demolition work that puts people on a lower level in danger.
Structural and load-carrying members on a floor stay until every story above that floor is gone.
No wall section more than one story high is left standing alone without side bracing, unless it was designed and built to stand that way and is still in safe shape. And every wall is left stable at the end of each shift.
Where the debris lands
When debris is dropped without a chute, the landing area is completely closed in with barricades. At least forty-two inches high. At least twenty feet back from the edge of the opening above. Warning signs go up at each level. And nobody removes debris down below until the dropping stops up above.
Nothing gets dropped outside the building walls unless that area is protected the same way.
Holes, openings, nails and the way in
A hole cover has to hold at least twice the weight of the people, equipment and material that could be on it at one time. It is marked with the word "hole" or "cover." And it is secured so wind, equipment or a boot cannot move it.
At a wall opening where you could fall four feet or more, and the bottom of the opening is lower than thirty-nine inches above the floor you are standing on, you get fall protection. A guardrail, a net, or a personal fall arrest or fall restraint system.
Nails sticking out of boards, planks or timbers get pulled, driven in or bent over as soon as the piece comes off the building.
And use only the stairs, passageways and ladders picked as the way in. The other ways get closed off, all the time.
Keep looking
As the work goes on, the competent person keeps checking for weak floors, weak walls and loose material. Nobody works there until it is shored, braced or made safe.
This next part is good practice, not the rule's words. If you open something up and find a pipe, a wire or a material nobody told you about, stop and tell your supervisor. And if the building does something you did not expect, a crack, a sag or a noise, get out and say so.
Talk it over
- Who is the competent person on this job, and where is the demolition plan kept?
- Where is debris landing today, and how is that area closed off?
Before you go
Survey and plan first. Utilities controlled. Top down. And nobody under the drop.