Morning, everybody. Today is block and brick. Masonry walls.
A masonry wall is at its best the day it is finished and tied into the building. Until then it is a tall stack of heavy things, held together by something that is still wet. So Washington's construction rule cares a lot about who is standing next to it.
This talk is for the masons, and for everybody else who walks past the wall.
The limited access zone
Whenever a masonry wall is being built, there has to be a limited access zone. That is an area alongside the wall that is clearly marked off to limit who goes in.
Here is what the rule says about it.
It is set up before the wall is started. Not after the third course.
Its size is equal to the height of the wall to be built, plus four feet. The way we picture that, for a wall that will be ten feet tall, the zone reaches fourteen feet out from the wall. The fourteen is our arithmetic. The rule just says height plus four feet.
It runs the whole length of the wall.
It goes on the side of the wall that will not have scaffold on it.
Only the people actively building the wall go in. Nobody else. Not for a shortcut, not to drop off material, not to have a look.
And it stays. The zone stays in place until the wall is supported well enough that it will not tip over or collapse. If the wall is over eight feet tall, the zone stays until the bracing requirements in the next part have been met. And those say the bracing stays until the permanent supporting parts of the structure are in place. So do not take the zone down just because a brace went up. That last line is how we read the rule, the careful way.
Bracing
Every masonry wall over eight feet tall has to be braced well enough to keep it from tipping over or collapsing. The one exception is a wall that is already supported well enough that it will not.
The bracing stays in place until the permanent supporting parts of the structure are in place.
So nobody pulls a brace because it is in the way. If a brace has to move, that is a question for the supervisor, not a favor for the forklift. That last line is plain sense, not the rule's words.
Cutting and chipping
Anyone cutting or chipping wears suitable eye protection. For stone cutters trimming stone or cutting holes, the rule says goggles.
Masonry saws keep their blade guard on. On a table saw, the dust is controlled with an exhaust or with water on the blade, and the operator and anyone nearby wear eye protection. On a hand-held saw, the operator wears eye protection and a respirator.
Silica dust had its own talk, so we will leave the dust there.
The mortar mixer
A mason's mortar mixer has a bar-type grill over the opening. And the guard has an automatic switch. When the guard is not in place, the switch stops the tub from turning and keeps the mixer from starting.
That grill is there because of hands and arms. Leave it on, and do not defeat the switch.
One more thing
The rule also has lines on setting stone with a derrick. Most crews will not see that, so it is not in this talk.
And here is some good practice, not the rule's words. Look at the bracing at the start of the day, and again after a hard wind or after something bumps it.
Talk it over
- Where is the limited access zone on this job, and how is it marked?
- Who looks at the wall bracing each morning?
Before you go
Zone up before the first block. Wall height plus four feet. Brace anything over eight feet. And the grill stays on the mixer.