Morning, everybody. Today is the material hoist, the one that takes drywall, block and buckets up the building so our backs don't have to. It saves a lot of stairs. Which is why, sooner or later, somebody looks at the empty platform going up and thinks, "Why walk?" This is part one of two. Part two is loading, the shaft, and what to report.
No riders
Here is the rule, plain. Nobody rides a material hoist. The only exception is for inspection and maintenance. Not to get to the fifth floor, not to ride up with the load to keep it steady, not because the stairs are blocked. The hoist has to be posted with the words "No riders allowed."
And nobody rides on top of a material hoist, a personnel hoist or a permanent elevator, except for inspection, maintenance, or putting in or taking down an elevator.
The personnel hoist is a different machine
A material hoist is built to carry material. On a multistory building where the trip up is more than sixty feet from ground level access, the rule requires a personnel hoist for the crew. If there is no way up but the stairs, take the stairs. That is plain sense.
What makes a personnel hoist different? The car is enclosed on all sides and the top, except the entrance, which has its own gate or door. The hoistway doors or gates have mechanical locks that can't be opened from the landing side. Electric contacts stop the hoist from moving when a door or gate is open. There is an emergency stop switch in the car, marked "stop." When it carries workers, an attendant gives the signals. Before it goes into service, it's inspected and tested under a competent person. After that it is inspected and tested at least every three months, with records kept for the job.
The landing gates
Every landing entrance to the hoistway, whether anybody is using that floor or not, has a gate or bars across the full width of the opening. They are painted in diagonal stripes, like black and yellow. The bars sit between thirty-six and forty-two inches off the floor, and the gates and bars have a latch.
That gate is the only thing between you and the open shaft. Keep it latched unless you're loading or unloading. That's plain sense, not rule text. Never lean through the gate to look up or down the shaft. The platform doesn't slow down for your arm.
Talk it over
- Has anybody ever seen someone ride a material hoist, and what did we do about it?
- Which landing gates on this job get left open, and why?
Before you go
Nobody rides. Stairs, or a personnel hoist. Gate latched.