Stacking and Storing Material

Lines in italics are for the reader, not the crew. How to read a talk

Printable version with sign-in sheet (PDF)

Read this out loud

Morning, everybody. Today is about where we put stuff.

Every job starts as a pile of material and slowly turns into a building. In between, that material has to sit somewhere. And a stack that leans a little on Monday has all week to think about it.

The basic rule

Washington's construction rule says material stored in tiers gets stacked, racked, blocked, interlocked or tied down some other way, so it cannot slide, fall or collapse.

Aisles and walkways stay clear, so people and equipment can move.

And material gets put where it is not in the way of, or a danger to, the crew, traffic or the public.

Inside the building

Stored material stays at least six feet back from any hoistway or floor opening.

It stays at least ten feet back from an outside wall, if that wall does not come up higher than the top of the stack. Think of a stack of board next to an open edge on an upper floor.

Floors have limits too. Inside a building, the safe floor load gets posted in storage areas, and we don't go over it. A slab on the ground is the exception. If you don't know what a floor can take, ask before the delivery shows up, not after.

Lumber

Pull the nails out of used lumber before you stack it.

Stack lumber on level, solid sills, up off the ground, so the pile is stable and holds itself up.

Once the stack is over four feet high, it gets cross strips.

And the rule caps a lumber stack at twenty feet, or sixteen feet if people handle it by hand.

Bags, brick and block

Bagged material gets stepped back as it goes up, and the bags get cross-keyed at least every ten bags high.

Cement and lime bags don't go over ten high, unless they are in a bin or enclosure built for it. And Washington adds something for the people handling those bags. Sealed eye protection, like goggles. And a long-sleeved shirt with a close collar and cuffs. Cement and lime burn skin.

Brick stacks stay at seven feet or under. A loose brick stack starts tapering in once it is four feet high.

Block gets stacked, not dumped in a loose pile. Over six feet, the stack tapers back half a block for each tier.

Pipe, poles and steel

Anything round wants to roll. Pipe, poles, bar stock and structural steel get stacked and blocked so they cannot spread or tip, unless they are in a rack. And the rule says people handling rebar wear heavy gloves.

Up on the scaffold

Don't store material on a scaffold or a runway beyond what is needed for the work going on right now. A scaffold is a place to work. It is not a shelf.

Good practice

This part is good practice, not the rule's words.

When a delivery shows up, somebody decides where it goes before it comes off the truck.

If you see a stack leaning, say so and fix it now. Don't walk around it for three days.

And don't climb a stack to get the piece on top.

Talk it over

  1. Where on this site is a stack that is leaning, or sitting in a walkway, right now?
  2. Who decides where a delivery gets dropped on this job?

Before you go

Stack it so it cannot slide, fall or roll. Keep it back from edges and openings. And keep the walkways open.

Short on time, or no one to lead it? Doc and Red can run this talk for you in the R Safety Hub app.

Get started

Reference (not read aloud). Washington: WAC 296-155-325(1)(a) (tiers secured against sliding, falling or collapse), (1)(b) (floor load limits posted and not exceeded, except floor or slab on grade), (1)(c) (aisles and passageways clear), (1)(f) (material located so it is not a hazard to employees, traffic or the public), (2)(a)(i) (not within 6 feet of a hoistway or inside floor opening, nor within 10 feet of an exterior wall that does not extend above the stored material), (2)(d) and (d)(ii), (d)(iv) (bags stepped back and cross-keyed every 10 high; cement and lime not over 10 high except in bins or enclosures; sealed eye protection and long sleeves with close-fitting collar and cuffs), (2)(e) (scaffolds and runways), (2)(f) and (f)(iii) (brick; blocks stacked, not thrown in a loose pile), (2)(g) (block over 6 feet), (2)(h) (lumber), (2)(i) and (i)(i) (cylindrical material; heavy gloves for reinforcing steel). Federal: 29 CFR 1926.250(a)(1), (a)(2), (a)(3), (b)(1), (b)(4) to (b)(9). The cement and lime clothing lines, the block-not-dumped line, cross strips over 4 feet and the rebar gloves were read in the Washington text; no matching federal sentence was seen in 1926.250. The federal text exempts single-family and wood-framed multi-family residential structures from posting floor loads; the Washington text read today does not say that. "Cement and lime burn skin" follows the rule's own words about cement and lime burns. "Think of a stack of board next to an open edge," "a scaffold is not a shelf" and the good-practice section are plain explanation, not rule text.